Millie West Tennis Facility Renovation
Renovate existing facility by replace existing courts, adding scoreboard, replace bleachers and add elevated seating/viewing platform
- Project Number: 204-18220-004
- Cost: $2,886,000
- Fund Source: Auxiliary
- Renovation/additional GSF: 65,500
- Project Start Date: January 2020
- Construction Start Date: July 2021
- Finish Date: January 2023
- Project Manager: Catherine Parker
- Design Team: McKinney & Company
- Contractor: Field Turf USA, Inc.
- Progress: Complete