Close menu Resources for... William & Mary
W&M menu close William & Mary

Martin Family Stadium

Martin Family Stadium Rendering
Martin Family Stadium Rendering
Martin
Martin ongoing construction at the Martin Family Stadium site. BCWH

This project will design and construct a 1,000 seat pre-engineered bleacher with a brick facade, a pre-fabricated press box, restrooms and team rooms.  The project will be designed to support additional seat build-out to 1,500.

  • Cost: $ 2,968,000
  • Fund Source: Private
  • Start Date: August 2010
  • Finish Date: April 2011
  • Design Team: BCWH
  • Contractor: Hourigan
  • Progress: Substantial completion was achieved on April 1st in preparation for the stadium dedication on April 16th during the last women's lacrosse game on April 17th.

 


John Graziani, Project Manager