Built in 1926, Ewell Hall is shared by several academic units and administrative offices in Arts and Sciences. The renovations will update life safety systems, ensure full accessibility, replace building systems which have exceeded life expectancies, and reconfigure the interior to suit future use by Health Sciences, while also improving circulation by connecting two structurally separated areas. The renovation will provide critical space for seminar and classroom space, teaching laboratories, core facilities, collaborative workspace, shared equipment rooms, and shared laboratory storage.

Project Details

  • Project Number: 204-18785-000
  • Construction Value: $20,300,000 (preliminary estimate)
  • Project Value: $29,000,000 (preliminary estimate)
  • Fund Source: State
  • Renovation Square Footage:  40,071 GSF
  • Project Start Date: September 2025
  • Construction Start Date: TBD pending state authorization and funding
  • Finish Date: TBD pending state authorization and funding
  • Project Manager: Adam Witkowski
  • Design Team: TBD
  • Contractor: TBD

Progress

A cost verification report has been received from the commonwealth approving detailed planning funds in the amount of $2,567,000 per item C-48 (2025) Chapter 725 Budget Bill. Program verification and development are needed to advance the project into the Schematic Design phase.

Building Committee

Adam Witkowski, Senior Project Manager
Ben Boone, Arts & Sciences Associate Dean for Educational Policy
Brennan Harris, Health Sciences Department Chair
Dan Pisaniello, University Architect
Marc Kelly, Executive Director of Facilities Operations
Mike Maddalena, AVP of Budget and Financial Planning
Stephanie Caligiuri, Assistant Professor of Health Sciences
Tim Dean, Director of Design & Construction
Student Representative (to be appointed by Arts & Sciences)

Existing exterior view of Ewell Hall from the Sunken Garden.
Photo by Alfred Herczeg, William & Mary