End of Summer Parking Lot Maintenance 8/4 - 8/13
Full Description
Due to the short window between the end of summer programs and the start of the fall semester we have a very accelerated schedule of maintenance.
Below is the upcoming schedule of milling, paving, and striping work occurring between 8/4 and 8/13.
Main Campus lots:- Boswell Lot (end to end) - August 5, 6, and 7
- Jones Hall - August 5
- Hunt Circle - August 6
- Lower Kaplan Lot (Fenced area) - August 10 and 11
- OTP Red (Parking Garage) - Concrete patching & Repair (TBD)
VIMS Campus:
- Hoxton Hall - August 4
- Nunnally Hall - August 10-11
- Triangle - August 12
- Sowers House - August 12
- Davis Hall - August 12
- Clayton House - August 12-13