Zable Stadium East Locker Rooms

The renovations of the east side of Zable Stadium modernized and update the men's and women's track locker rooms. The project also improved indoor air quality and ventilation in the spaces, and provided for the installation of mini-split mechanical systems, and waterproof the east grandstands.

Project Details

  • Project Number: 204 – 323134
  • Cost: $2,900,000
  • Fund Source: Donor Funded
  • Renovation GSF: 4,800 square feet
  • Project Start Date: January 2022
  • Construction Start Date: December 2024
  • Finish Date: April 2025
  • Project Manager: Anne Baskerville (Design) / Patrick Hermes (Construction)
  • Design Team: Matthew G. Burton Architect, LLC
  • Contractor: GC Commercial, Inc.

Building Committee

Abby Houser, Associate Budget Director
Brian Mann, Director of Athletics
Dan Pisaniello, University Architect
Patrick Hermes, Project Manager
Richard Whitmore
, Deputy Director of Athletics