Memorial To The Enslaved
Project designs and constructs a memorial to persons enslaved by W&M. Concept design is a hearth – the result of a worldwide competition. Memorial will be located to the south of the Wren Building.
- Project Number: 204 – 80002
- Cost: $2,977,000
- Fund Source: Private Funds
- Project Start Date: June 2019
- Construction Start Date: Jun 2021
- Finish Date: May 2022
- Project Manager: Amber Hall
- Design Team: Baskervill
- Contractor: Kjellstrom & Lee, Inc.
Building Committee
Amy Sebring, Chief Operating Officer
Chon Glover, Chief Diversity Officer
Ed Pease, Architect and Adjunct Professor
Gregg Shipp / Amber Hall, Project Manager
Jody Allen, Assistant Professor of History & Director of the Lemon Project
Susan Kern, Director of the Historic Campus
Warren Buck, Adjunct Professor of Physics
Van Dobson (Design) / Sam Hayes (Construction), Chief Facilities Officer