Dillard Soccer Field Revision
Project included a master plan design for the overall site, lighting for the field, a scoreboard for the field, ballstop netting and a 12'x20' prefab storage building.
- Project Number: 270030
- Cost: $1,013,000
- Fund Source:
- Renovation/additional GSF: 2,300
- Project Start Date: Feb 2020
- Construction Start Date: June 2021
- Finish Date: August 2021
- Project Manager: Catherine Parker
- Design Team: Draper Aden Associates
- Contractor: FieldTurf