Project included a master plan design for the overall site, lighting for the field, a scoreboard for the field, ballstop netting and a 12'x20' prefab storage building.

  • Project Number: 270030
  • Cost: $1,013,000
  • Fund Source:
  • Renovation/additional GSF: 2,300
  • Project Start Date: Feb 2020
  • Construction Start Date: June 2021
  • Finish Date: August 2021
  • Project Manager: Catherine Parker
  • Design Team: Draper Aden Associates
  • Contractor: FieldTurf
: