Century Project - Busch Field Team Facility

2,900 sf one-story building that provides public male and female toilets and team support facilities for the Women’s Athletic program. The new building contains permanent team locker facilities, public toilet facilities to support spectators at Busch Field and Millie West Tennis Courts, goalies’ gear storage, a trainer’s room and a VIP viewing component on the rooftop. The filming platform has been excluded. The design effort for the Team Facility encompasses stormwater infrastructure for the surrounding service roadway and site integration of the tennis courts to the East of the new facility.
- Project Number: 204-90011
- Cost: $2,544,540
- Fund Source: Athletics
- Renovation/additional GSF: 2900
- Start Date: February 2018
- Finish Date: estimated January 2020
- Project Manager: Mike Terrell
- Design Team: McKinney & Company
- Contractor: Virtexco