Blow IT Data Center Renovation
Installation of a new HVAC system for computer rack cooling to correct the hot and cold aisle air mixing; installation of redundant power sources - two electrical buses (A&B) for scalability and ease of maintenance: and, for uninterruptible power supply, two new UPSs were installed and backed up by a new generator power source. The generator is sized to handle the loads currently on the existing generator.
- Project Number: 204-18112-003 -- DEB PC# 204-A9204-005
- Cost: $2,710,000
- Fund Source: Debt (0815)
- Renovation/additional GSF: 56, 000
- Start Date: Mar 2017
- Construction Start Date: July 2021
- Finish Date: Dec 2022
- Project Manager: Adam Witkowski
- Design Team: Clark Nexsen