Blow Hall Roof and Cupola Restoration
Project Details
- Project Number: 204 – 20014
- Cost: $2,540,000
- Fund Source: Maintenance Reserve
- Project Start Date: May 2020
- Construction Start Date: June 2024
- Finish Date: September 2025
- Project Manager: Matthew Rossi
- Design Team: Mesick Cohen Wilson Baker Architects, LLP
- Contractor: TST Tactical Defense Solutions Inc
Building Committee
Abby Houser, Associate Budget Director
Brian Crystal, Director of Operations & Maintenance
Dan Pisaniello, University Architect
Matthew Rossi, Project Manager
Sean Hughes, Chief Business Officer