The project supported a study, design, and construction to examine and improve accessibility issues at facilities not targeted for renovation within the next decade, and/or improvements to various campus locations that impede accessibility. This particular project added an elevator and renovated public restrooms to meet ADA standards. 

  • Project Number: 204-18002-01
  • Cost: $2,207,395
  • Fund Source: Virginia College Building Authority
  • Renovation/additional GSF: 1,812
  • Start Date: Jan 2013
  • Finish Date: Sep 2018
  • Project Manager: Ben Mulherin
  • Design Team: Clark Nexson
  • Contractor: J.W. Enoch
  • Progress: Completed