Wren Building ADA Ramp

Design and install a new ADA ramp to the south door of the building.

  • Project Number:  0101-002-17/204-18019
  • Cost: $499,750
  • Fund Source: Private funds, Maintenance Reserve
  • Renovation/additional GSF:  
  • Start Date: Nov 2017
  • Finish Date:  estimated Jan 2019
  • Project ManagerAdam Witkowski
  • Design Team: Mesick Cohen Wilson Baker
  • ContractorReisbeck Contracting
  • Progress:
                  Request for Proposal:
                  Contract Awarded: 11/2017
                  Working Drawings:  05/2018
                  Code Review:  05/2018
                  Permit Award:  10/2018
                  Construction Start:  10/2018
                  Construction Completion:  02/2019
  • Notes
    1. 9/26/18 : The project has been approved by the Design Review Board and Department of Historic Resources with minor comments.  Construction is expected to begin this month.
    2. 11/08/18  The project has been approved by the Design Review Board and Department of Historic Resources with minor comments.  Working drawings (WDs) are complete and permit is approved. Contractor selected and construction is expected to begin this month.