Millie West Tennis Facility Renovation
Renovate existing facility by replace existing courts, adding scoreboard, replace bleachers and add elevated seating/viewing platform
- Project Number: 204-18220-004
- Cost: $3,000,000
- Fund Source: Auxiliary
- Renovation/additional GSF: 65500
- Project Start Date: Jan 2020
- Construction Start Date: July 2021
- Finish Date: Feb 2022
- Project Manager: Michael Terrell
- Design Team: McKinney & Company
- Contractor: TBD
- Progress: In Design Phase