Landrum Hall

 Standard File

The residential space in the 1958 era, 221-bed facility will be renovated in order to bring the facility into compliance with current building code, replace 59-year old building systems and replace interior finishes with modern materials and design, similar to the work achieved in Chandler Hall. 

  • Project Number:  204 – 18100 – 006
  • Cost: $19,463,177     
  • Fund Source: CWM debt  (9c Bond)
  • Renovation/additional GSF: 59,976
  • Start Date: 06/2016
  • Finish Date:  estimated Oct. 2018
  • Project ManagerJeff Brancheau, Will Koeck
  • Design Team: Clark-Nexsen        
  • Contractor: W.M. Jordan
  • Progress:
                  Request for Proposal:  06/2016
                  Contract Awarded: 11/2016
                  Working Drawings:  03/2017
                  Code Review:  03/2017
                  Permit Award:  06/2017
                  Construction Start:  06/2017
                  Construction Completion: est 10/2018
  • Notes
    1. 9/26/18 New building mechanical, plumbing and fire sprinklers systems are about 90% complete with interior wall framing and drywall also nearing completion. New elevator has been installed and the remaining scope includes interior electrical, interior finishes and sitework. Estimated completion has shifted to October 30th.
    2. 11/08/18   Estimated completion has shifted from October 30th to December 7th.