Dillard Scene Shop

Relocate “Scene Shop” operations from PBK to a new facility at the Dillard Complex.

  • Project Number:  204 – 18292-001
  • Cost: $
  • Fund Source: State
  • Renovation/additional GSF:
  • Start Date: Dec 2017
  • Finish Date:  estimated Jan 2019
  • Project Manager:  Catherine Parker
  • Design Team: CHA
  • Contractor:  TBD
  • Progress:
                  Request for Proposal:
                  Contract Awarded: 12/2017
                  Working Drawings:  06/2018
                  Code Review:  06/2018
                  Permit Award:  09/2018
                  Construction Start:  09/2018
                  Construction Completion:  01/2019
  • Notes
    1. 9/26/18 WD design submitted to CRT on 6/14/18 including Delegated Design for Sprinkler, Delegated Design for PEMB was rejected and was revised.  Comments from CRT for WD set received on 8/1/2018.  CRT issued construction permit for sitework and utility relocations only on 8-31-18.  Revising design now and will be coordinating with CRT for a submission for week of 9/24/18.