Accessibility Infrastructure

The project supports a study, design, and construction to examine and improve accessibility issues at facilities not currently targeted for renovation within the next decade, and/or improvements to various campus locations that impede accessibility.

  • Project Number:  204 – 18002
  • Cost: $2,889,456       
  • Fund Source: State
  • Renovation/additional GSF:
  • Start Date:
  • Finish Date:
  • Project ManagerBen Mulherin
  • Design Team: Clark-Nexsen        
  • Contractor: Pembroke Construction     
  • Const:  JW Enochs
  • Progress:
                  Request for Proposal:
                  Contract Awarded:  01/2013
                  Working Drawings:  10/2016
                  Code Review:  10/2016
                  Permit Award:  06/2017
                  Construction Start: 07/2017
                  Construction Completion:  est 10/2018
  • Notes
    1. 9/26/18 The Adair Hall elevator construction will be completed in September and pathway construction is planned for an October finish.
    2. 11/08/18 The Adair Hall elevator construction was completed last month and pathway construction is planned for a mid-November finish.