Zable Stadium Improvements

The project supports renovation and improvements which will include significant expansion of the west stands, improved existing seating, new accessibility and restroom facilities, a public address system, and code required upgrades.

  • Project Number:  204-90005, 204-11812-01
  • Cost: $ 27,983,000.00
  • Fund Source: Private 0302/9d
  • Renovation/additional GSF: approx. 110, 000
  • Start Date: Aug 2013
  • Finish Date:  Feb 2017
  • Project Manager:  Mark Ballman
  • Design Team:  BCWH, Inc
  • Contractor:  Barton Malow Company
  • Progress:
                  Request for Proposal: 08/2013
                  Contract Awarded: 11/2013
                  Working Drawings:  10/2014
                  Code Review:  10/2014
                  Permit Award:  04/2015
                  Construction Start:  04/2015
                  Construction Completion:  02/2017
  • Notes
    1. Temporary Certificate of Occupancy was re-issued for an additional 30 days 1/13/17 to 2/13/17 with a "date certain" list for remaining deficiencies.