McLeod Tyler Integrative Wellness Centre

Construct a wellness center to house, integrate and enhance the functions of the existing Student Health Center, the Counseling Center (currently in Blow Hall), a Health Promotions office and selected Recreation activities (yoga, massage, expressive movement, etc.).  The project will create a center which is welcoming and holistic and which can attract all students in order to aggressively promote wellness through prevention vice focusing exclusively upon intervention. 

  • Project Number:  204-18192 & 18112-02
  • Cost: $19,000,000
  • Fund Source: CWM Debt, CWM Aux, Private Funds,
  • Renovation/additional GSF:  30,864
  • Start Date:  Oct 2015
  • Finish Date:  Aug 2018
  • Project ManagerCatherine Parker
  • Design Team: EYP
  • Contractor:  Whiting-Turner
  • Progress:
                  Request for Proposal:
                  Contract Awarded: 10/2015
                  Working Drawings:  02/2017
                  Code Review:  02/2017
                  Permit Award:  09/2017
                  Construction Start:  09/2017
                  Construction Completion:  08/2018
  • Notes
9/26/18 : Construction is substantially complete with punch list remaining. Occupants have moved and are operating in the facility as of August 8th. Ribbon cutting held on August 28th