Integrated Science Center Phase III

The project will construct a facility, designed for scientific research in existing applications (Applied Science, Biology, Chemistry, and Psychology), future inter-disciplinary programs, and computer modeling. 

  • Project Number:  204-17650
  • Cost: $  74,769,176
  • Fund Source:  Virginia College Building Authority
  • Renovation/additional GSF:  113,000
  • Start Date:  Mar 2013
  • Finish Date:  Jul 2016
  • Project ManagerOot Singhaseni
  • Design Team: EYP
  • Contractor:  Whiting Turner             
  • Progress:
                  Request for Proposal:
                  Contract Awarded: 03/2013
                  Working Drawings:  10/2014
                  Code Review:  11/2014
                  Permit Award:  02/2015
                  Construction Start:  05/2015
                  Construction Completion:  07/2016