Dupont Hall HVAC

To improve humidity control for the current HVAC system in Dupont Hall. 

  • Project Number:  18100-008
  • Cost: $ 1,532,717
  • Fund Source:  CWM Aux
  • Renovation/additional GSF:  
  • Start Date:  Feb 2016
  • Finish Date:  Aug 2018
  • Project ManagerBen Mulherin
  • Design Team: Mathew G. Burton
  • Contractor:  GC Solutions & Daikin
  • Progress:
                  Request for Proposal:
                  Contract Awarded: 02/2016
                  Working Drawings:  12/2017
                  Code Review:  12/2017
                  Permit Award:  05/2018
                  Construction Start:  04/2018
                  Construction Completion:  08/2018
  • Notes
    1. 9/26/18 : Acknowledgement of Substantial Completion issued on 8-13-18.  Revised HECO-2 was approved on 7-16-18.