Fraternity Housing (New)
- Cost: $25.8 million
- Fund Source: 9c Bonds
- GSF: 72,600 plus 8,845 for Phase I & II of the Community Building
- Start Date: April 2012
- Finish Date: June 2013
- Design Team: Moseley - Treanor Associates
- Contractor: WM Jordan
- Progress: Design began in April 2011. The Design Review Board (DRB) and the state Art and Architectural Review Board (AARB) gave final approval to elevations/exterior designs in September 2011. Work began in early February for a new 115 space parking lot adjacent to William & Mary Hall that replaces the lot being taken for the new project. Building construction will begin May 2012. Sustantial completion is scheduled for July 2013.
Building Committee
Joe Martinez, Project Manager
Anna Martin, Vice President, Administration
Wayne Boy, Associate Director of Facilities Planning, Design, and Construction
Dave Shepard, Associate Vice President, Facilities Management
Bob Avalle, Director of Operations and Maintenance, Facilities Management
Joe Martinez, Deputy Director of Facilities Planning, Design, and Construction
Martha Sheets, Senior Planner
Ginger Ambler, Vice President, Student Affairs
Mark Constantine, Assistant Vice President for Student Affairs, Student Activities
Deb Boykin, Director, Residence Life
Chris Durden, Director of Housing Operations, Residence Life
Anne Arseneau, Associate Director, Student Activities